2024 Construction Information and taxi routes (Reference Taxi Maps below)
Phase 1
50 working days (not calendar days)
Longest of the 3 Phases
RWY 1L/19R Closed as well as TWY A abeam TLN DD to the south closed
Building of new TWY H and A2 as well as building the new TWY A3 straight across from TWY J and removing the excess pavement on the north side of A1
Hotspot will be at the TWY A, A2, A3 intersection
TWY A starting at TXL DD and south will be one in one out due to TWY A closure
RWY 13/31 will be open for the duration of this phase however, due to extreme complexity, it will not be advertised as the RWY in use, and will only be usable on a case-by-case basis for arrivals and departures (i.e., taildraggers during high crosswind scenarios)
During North Flow, if a ramp run up is not completed, the runup are for RWY 31 will be used
Phase 2
5 working days
RWY 1L/19R and RWY 13/31 closed as well as TWY A North of the new TWY A3 to A4 closed
Removing the old TWY A2
Hotspot at the new TWY A3 and A due to one in one out from TLN DD north to Christiansen Jet Center
If ramp runup is not completed on the west side during south flow, runups will be done at the 1L runup area
All arrivals parking on the west side will transition via TWY J to the new TWY A3
Phase 3
10 working days
RWY 13/31 closed
Both RWY 1L/19R and RWY 1R/19L will be open
Removing the old TWY A3
TWY A North of the new TWY A3 to A4 closed
Hotspot at the new TWY A3 and A due to one in one out from TLN DD north to Christiansen Jet Center
If ramp runup is not completed on the west side during south flow, runups will be done at the 1L runup area
All arrivals parking on the west side will transition via TWY J to the new TWY A3